24″ Wellsboro Pipeline East Creek Slip Remediation
The Hillis Group was contacted to proactively restore recently discovered soil fractures on a steep slope. During the initial exploratory excavations, numerous spring seeps, organic materials, and timbers were discovered which resulted in more of an extensive repair than initially designed. Over 6,500 cubic yards of soils were excavated from…