Spread 18
The Hillis Group completed 13.6 miles of Stress Corrosion Cracking Hydrostatic testing combined with 6,852 LF of take up and re-lay of 24” pipe. This project consisted of pipe replacements, building, maintaining, and removal of temporary access roads, multiple creek crossings, difficult terrain (rock and steep slopes), two separate caliper pig runs, drying of the line, and critical tie-in dates to ensure the line was in service to supply customers.